The post maintenance of the automatic partition assembler insert machine mainly includes the following aspects:
1. Electrical maintenance: Clean and wipe the dust outside the motor and electrical box, and spray the dust inside the electrical box with cleaning agent. Check and organize electrical circuits and contact points of various electrical appliances, requiring reasonable layout, reliable connection, safe and reliable work.
2. Bed and exterior maintenance: Clean the surface and dead corners of the machine tool to ensure that the paint is natural and the iron is shiny. Remove and wash all protective covers and plates to achieve internal and external cleaning. Remove burrs from the guide rail surface.
3. Maintenance of gearbox and feed mechanism: Each operating handle should be flexible and reliable, and any missing handle balls should be supplemented. Clean the exchange gear and shaft sleeve of the hanging wheel box to achieve correct assembly position and moderate meshing clearance. Check for any noise in the transmission system and replace worn parts or oil according to the situation.
4. Gear head maintenance: Wipe and inspect each sliding surface to remove burrs. Adjust the gear head and slider to achieve even fit and moderate clearance. Wipe the horizontal screw to achieve flexible tooth movement.
5. Workbench maintenance: Clean the workbench and oil pan to ensure that there is no oil or dust in the grooves and taper holes. Check the wear and lubrication of the dividing worm gear, make up for any defects as much as possible, and keep records.
6. Daily maintenance: Before starting up at work, check if all electrical buttons, switches, and transmission handles are in the correct positions. Make daily equipment inspections and shift handover records.
7. First level maintenance: The corrugated cardboard partition machine tool has accumulated 2500 hours of operation (equivalent to half a year in a two shift system) for first level maintenance, with a downtime of 0.5 hours per complexity factor, mainly carried out by operators and assisted by maintenance workers.
When performing maintenance, it is necessary to follow the cardboard partition assembler machine‘s operating manual and maintenance procedures to ensure that the maintenance work is carried out correctly. At the same time, the operation status of the equipment should be regularly checked to promptly identify and solve potential problems, in order to extend the service life of the equipment and ensure smooth production.
If you are also interested in this machine,please don’t hesitate to contact us:
Overseas manager: Tom Wang
Email:cartonmachine.tomwang@aliyun.com
Phone/Wechat/Whatsapp:+86 13303078975
Post time: Dec-18-2024